Monday Madness
12 min read
I’ll take a try at this.
We are going to be spreading rock 2 inches deep, 10 feet wide on one and a half miles of road.
Let’s find out how many cubic feet this gives us.
10 x 7920 x 2/12 which is 13200 cu. ft
Expressed as cubic yards 13200 / 27 which is 488.89 cu. yds
Which would be brought in 488.89 / 10 trips by truck, or 48.889 trips
How long does our project take? (just deal with working time. Don't consider lunch, sleeping, etc.)
It takes 31 minutes to load the truck, haul and spread, and then return to the pit.
So it would take 31 x 48.889 = 15155.556 minutes
This is 252.59 hours or 10 ½ days.
How big is our pit on completion?
So this means 13200 cu. ft / 1.1 = 12000 cu ft in situ -The rock has a swell factor of 10%,
Hole size is 12000 cu ft
So lets express that in layman terms.
Length of hole = 12000 / (5 x 60) = 40 ft
So hole is 5ft deep . 60ft wide , 40ft long.
Thats my attempt.
I won't critique your answers at this point… but I suggest that you not only review units, but also logic.
check your math.2/36 x 10/3 x 2640 = 492.3 cu yrds
rock spread on the road is figured as "loose" yards. No further shrink or swell necessary.Since you won't be able to fill every nook and craney the 10% difference applied to the trucks seems reasonable
@terry1966,
I think that the swell factor has you confused. The material in the truck (and on the road) takes up 10% more space than the material in the bank.
@otisx,
Each trip takes 31 minutes and delivers a maximum of 10 cubic yards.
To clarify what I meant. The amount needed would be less than the calculated volume and the 10% would apply to the road as well.Since you won't be able to fill every nook and craney the 10% difference applied to the trucks seems reasonable
rock spread on the road is figured as "loose" yards. No further shrink or swell necessary.
It took about 22.73 hours and you ended up with a pit 60' x 5' x 39.6'
2/36 x 10/3 x 2640 = 488.89 cu yrds
That would be the volume of the space you wanted to fill. Since it's loose you need 440 cu yrds.
Total trucks = 44
Time would be trucks x 31 min = 1364 or 22.73 hrs
The resulting pit would be 440 = 60/3 x 5/3 x 13.201 (13.2301 is yards) So in feet the pit is 60' x 5' x 39.603'
2/36 x 10/3 x 2640 = 488.89 cu yrds - on the road.
That would be the volume of the space you wanted to fill. Since it's loose you need 440 cu yrds. - nope. Check your math (and this would be in the pit)
@terry1966,
Material swells 10%. You can't shrink it 10%. Check your math.ok simple enough then 10% less than 22,809,600 is 20,528,640
sorry but you lost me tomk.Material swells 10%. You can't shrink it 10%. Check your math.
20,528,640 cubic inches of solid rock swells 10% to 22,809,600 cubic inches of loose gravel.(which is the amount we need to fill the road.)
so nothing got shrunk as far as i'm aware and can't see where my calcs/logic are wrong with my current understanding of swell.
If we excavate 20,528,640 cubic inches of material and it swells 10% we would have:20,528,640 cubic inches of solid rock swells 10% to 22,809,600 cubic inches of loose gravel.(which is the amount we need to fill the road.)
20,528,640 + 2,052,864 = 22,581,504 cubic inches. That doesn't appear to be what you said.
@oldman960,
That is the correct calculation for material required to be spread… and therefore the correct truck loads. But - how many trips?2/36 x 10/3 x 2640 = 488.89 cu yrds
That would be the volume of the space you wanted to fill.
Total trucks = 48.9
440 cubic yards swelled 10% would be:The resulting pit would be 440 = 60/3 x 5/3 x 13.201 (13.2301 is yards) So in feet the pit is 60' x 5' x 39.603'
440 + 44 = 484 cubic yards. Is this the number you are looking for?
That is the first totally correct answer.
The pit is 60 ft x 40 ft x 5 ft.
It took 48.9 loads of material which gives 49 trips to be made which takes 25 hours and 19 minutes.
otisx nearly had it but he had me making .889 of a trip and I had to make the whole trip no matter how many yards the truck was carrying. (truthfully, I actually put all 10 yards in the truck each of the 49 trips
The trip vs load thing is what confused otisx. terry1966 and oldman960 went awry with the swell factor. Here is what I think happened:
If you swell 1 by 10% you get 1.1. However, if you take 90% of 1.1 you get .99. These are not equal and opposite actions.